When did Governor Andrew Cuomo's administration appoint the study board for Highmark Stadium?

Governor Andrew Cuomo's administration appointed Buffalo Mayor Byron Brown and Niagara Falls Mayor Paul Dyster to a new study board on the 10th of February 2014. This group included Lt. Gov. Robert Duffy and Empire State Development President Kenneth Adams.

What is the total estimated cost for the construction of Highmark Stadium as of August 2023?

The estimated cost for the stadium reached $1.7 billion by the 9th of August 2023. This figure increased by $300 million due to higher labor and material costs.

Where will the new Highmark Stadium be located in relation to existing landmarks?

The 67,000 capacity facility will be built adjacent to Erie Community College's south campus across the street from the existing Highmark Stadium. The old stadium will be demolished once the new one completes.

How much money does New York State contribute to the financing of Highmark Stadium?

Six hundred million dollars comes from New York State while Erie County contributes $250 million. Taxpayers will pay $850 million of the construction cost under the agreement with New York State.

When did steel beam assembly begin at the Highmark Stadium construction site?

Steel beam assembly started in March 2024 following nearly complete excavation work. Concrete pouring also began that same month during the early stages of structural development.